Red Head® Epcon® Installation Steps for
For more information about Red Head® products go to the Red Head® website at: |
![]() |
Drill proper size hole. Clean out hole from botton with forced air. Complete hole preparation with use of a brush and repeat cleaning with forced air. (leave no dust or slurry). Please, always protect your eyes from flying debris by wearing safety glasses. |
![]() |
When starting new cartridge or nozzle, dispense and discard enough adhesive until a uniform grey color is achieved. insert nozzle into the bottom of the hole and fill to 1/2 the hole depth. |
![]() |
Insert selected rod slowly by hand into the bottom of the hole with a slow twisting motion. This insures the adhesive fills voids and crevises uniformly. |
![]() |
See the respective cure time charts for set-up time. After the recommended cure time is met, install and tighten fixture into place. |
Return to Acrylic: Epcon A7
Return to Epoxy: Epcon C6 and Epcon G5